What Is an IPD Project? A Plain-Language Guide to Integrated Project Delivery

Integrated project delivery (IPD) is a construction delivery method in which the owner, designer, contractor and key trade partners sign one multi-party agreement, share cost information openly, and can tie part of their compensation to the project’s total performance.

Complex industrial construction projects can expose the weaknesses of a fragmented delivery process. Equipment vendors, designers, general contractors, rigging teams, electrical contractors, mechanical trades, and plant operations may all have information that affects the project, but they are often brought into the conversation at different times. Integrated project delivery brings the key participants together earlier so they can plan the project as one team rather than solve conflicts after construction begins.

What is an IPD project?

An IPD project is a project in which the parties responsible for designing and building the work make major decisions together, share information openly, and align their financial outcomes with the overall success of the project.

Integrated project delivery, commonly called IPD, is a construction delivery approach that brings the owner, designer, contractor, and important trade partners into the project early. The team collaborates on design, cost, schedule, constructability, procurement, and field execution before major decisions become expensive to change.

Important features of integrated project delivery include:

  • Early trade-partner involvement. Contractors and specialized trades contribute practical knowledge while the design is still developing.
  • A multi-party agreement. Key participants work under a contract structure that defines shared responsibilities and project objectives.
  • Shared risk and reward. A portion of the participants’ compensation may depend on the project’s total performance, not only their individual scopes.
  • Open-book communication. Cost information, estimates, contingencies, and project risks are reviewed transparently.
  • Collaborative decision-making. Major issues are evaluated by the appropriate project leaders instead of being passed between separate contractual silos.

IPD is more than holding additional coordination meetings. It changes when people join the project, what information they share, and how they are encouraged to solve problems.

Who signs an IPD contract?

A formal IPD project commonly uses a multi-party agreement signed by the principal participants — typically the owner, the designer, the contractor, and the important trade partners. Instead of the owner holding separate contracts that isolate designers, contractors, and trades, the agreement connects the principal participants through common project goals and defined decision-making procedures.

IPD principles can also be applied without a formal multi-party contract. A project may use early trade involvement, open-book estimating, shared planning, and collaborative meetings under another delivery method. However, using a few collaborative practices does not automatically create a formal IPD project.

The practical test of a formal IPD project is therefore not collaborative language. It is whether the key trade partners signed the same multi-party agreement as the owner, the designer, and the contractor.

How is IPD different from design-bid-build and other delivery methods?

The biggest difference between integrated project delivery and traditional construction delivery is the timing and structure of collaboration. In design-bid-build, contractors bid a completed design under separate contracts; in IPD, the owner, designer, contractor, and key trades work under one multi-party agreement early enough to influence the design.

Under design-bid-build, the owner hires a designer to complete the design. Contractors then bid on the completed documents, and the selected contractor builds the project. This approach creates a clear sequence, but it often limits contractor and trade input during design.

For straightforward work with a stable scope, design-bid-build may be appropriate. On a complicated industrial project, however, the sequence can create problems. A designer may develop a layout before the rigging contractor evaluates equipment access. Utility routes may be finalized before equipment vendors confirm connection requirements. Major machinery may be ordered before the team resolves foundations, installation paths, or commissioning sequences.

Other common methods offer different levels of integration:

Design-build places design and construction under one primary contract. This can simplify owner communication and support earlier contractor involvement. However, design-build does not necessarily include shared financial risk and reward among the owner, designer, builder, and key trades.

Construction management at risk allows a construction manager to join during design, provide estimating and constructability input, and later serve as the general contractor. The owner usually maintains separate contracts with the designer and construction manager. Collaboration can begin early, but the contractual incentives remain different from formal IPD.

Traditional general contracting may provide strong project management and trade coordination after award. Still, key installation contractors may not influence equipment layouts, structural design, delivery routes, or procurement decisions soon enough.

Comparison pointIntegrated project deliveryDesign-bid-buildDesign-buildConstruction management at risk
Contract structure and signatoriesOne multi-party agreement connects the principal participants — owner, designer, contractor, and important trade partners — through common goals and defined decision-making procedures.The owner holds separate contracts that isolate designers, contractors, and trades.Design and construction sit under one primary contract, which can simplify owner communication.The owner usually maintains separate contracts with the designer and the construction manager, who later serves as general contractor.
Risk and reward allocationShared. A portion of participants’ compensation may depend on the project’s total performance, not only their individual scopes.Allocated inside each separate contract rather than across the team; issues pass between contractual silos.Does not necessarily include shared financial risk and reward among the owner, designer, builder, and key trades.Contractual incentives remain different from formal IPD.
When trade partners joinEarly. Contractors and specialized trades contribute practical knowledge while the design is still developing.After the design is complete and bid, which often limits contractor and trade input during design.Can support earlier contractor involvement than design-bid-build.The construction manager can join during design to provide estimating and constructability input.
Cost information and decisionsOpen-book: costs, estimates, contingencies, and risks are reviewed transparently, and major issues are evaluated by the appropriate project leaders.Pricing is set by bids on completed documents.One primary contract consolidates design and construction communication with the owner.The construction manager provides estimating and constructability input during design.
Comparison of the delivery methods as described in this article.

In integrated project delivery, a machinery installer or rigging contractor can review a proposed equipment layout before walls, roofs, platforms, or utility systems restrict access. An electrical contractor can evaluate service capacity while equipment specifications are being finalized. A foundation contractor can coordinate machine loads and anchor requirements before concrete placement.

This early input does not eliminate project risk. It gives the team more time to identify, assign, and reduce that risk before it reaches the field.

When does IPD fit a plant equipment installation?

Integrated project delivery often makes the most sense when a project has many technical interfaces, an aggressive schedule, evolving equipment information, or extensive coordination between trades — the conditions that define battery plants, automotive expansions, and other plant equipment installations.

Battery plants are a strong example. Their projects may include manufacturing equipment, clean rooms, dry rooms, process utilities, air handling systems, fire protection, electrical infrastructure, automation, material handling, and specialized equipment installation. A change to one system can affect several others.

Automotive facilities present similar challenges. A production expansion may involve stamping presses, robotic assembly systems, conveyors, paint systems, ovens, air handlers, electrical upgrades, foundations, and utility connections. The plant may also need to maintain current production while construction proceeds.

Integrated project delivery can help these projects by involving the people who understand installation requirements before the design is fixed. Early planning can address questions such as:

  • Can the equipment pass through the proposed building openings?
  • Where will cranes, gantries, trailers, and forklifts operate?
  • Does the slab support the equipment and installation method?
  • When must long-lead machinery be ordered?
  • Where will equipment be stored if it arrives early?
  • Which utilities must be available before installation?
  • Can mechanical and electrical trades work after the equipment is set?
  • What work must occur during shutdowns or off-shift windows?
  • How will OEM technicians participate in startup and commissioning?

Open-book cost management also allows the team to compare decisions based on total project value. For example, a larger temporary opening may add structural cost but eliminate equipment disassembly, reduce rigging time, and protect the schedule. In a fragmented process, each cost may be considered separately. An IPD team can evaluate the combined effect.

When does IPD not fit a project?

Integrated project delivery is not the right answer for every project. For straightforward work with a stable scope, design-bid-build may be appropriate, because the added planning structure of IPD has less to resolve when the scope is already fixed.

IPD requires transparency, early commitment, disciplined cost management, and participants who are willing to place project outcomes ahead of narrow scope interests. An owner who cannot share cost information openly, cannot commit trade partners early, or cannot make timely decisions will carry the cost of the structure without gaining its benefit.

Selecting participants on lowest initial price without evaluating team behavior can also undermine the purpose of IPD. Before committing to the delivery method, owners should confirm the project has enough complexity to justify the added planning structure — uncertain equipment information, overlapping design and construction, major prefabrication, phased turnover, active operations, or a fixed production launch date.

For complicated manufacturing facilities, battery plants, automotive expansions, and schedule-driven industrial installations, that effort can create a more buildable plan and fewer field conflicts.

What does a rigging and installation trade partner do on an IPD team?

On an IPD team, a rigging and installation trade partner reviews equipment layouts, access routes, lift plans, slab and foundation loads, storage, utility readiness, and commissioning sequences while the design can still change, instead of receiving a finished drawing set at bid time.

LMM’s capabilities fit the practical coordination needs of these projects. Our industrial services include project management, machinery moving, crane service, rigging, millwright work, transportation, storage, electrical support, mechanical work, foundations, logistics, fabrication, demolition, and engineering coordination.

LMM also supports EV battery equipment, automated production systems, automotive line relocations, utility interconnections, and commissioning preparation. Our resources include cranes with lifting capacities up to 550 tons, more than 500 pieces of specialized equipment, and 3D lift-planning capabilities for complex lifts.

These services allow LMM to contribute meaningful field information during planning, not only after equipment reaches the site.

How should owners prepare for IPD and select trade partners?

Owners should set clear project goals, confirm the project is complex enough to justify the added planning structure, define decision authority in the agreement, and choose participants based on their ability to collaborate, plan, and solve problems. Selecting the lowest initial price without evaluating team behavior can undermine the purpose of IPD.

Before committing to the delivery method, owners should consider whether the project has enough complexity to justify the added planning structure. IPD may be especially useful when the project includes uncertain equipment information, overlapping design and construction, major prefabrication, phased turnover, active operations, or a fixed production launch date.

Owners should also prepare to make timely decisions. Collaborative decision-making does not mean every participant votes on every issue. The agreement should define who has authority, how decisions are elevated, and what happens when the team cannot reach agreement.

When evaluating installation and trade partners, ask:

  • Can the contractor contribute during design and preconstruction?
  • Will the contractor share realistic estimates and schedule assumptions?
  • Can the team identify installation constraints before equipment is purchased?
  • Does the contractor self-perform important portions of the scope?
  • Can it coordinate rigging, transportation, storage, mechanical placement, electrical connections, and commissioning support?
  • Does it have planning tools that help other participants understand the work?
  • Can it provide examples of coordinating several trades on industrial installations?
  • Does its project team have the authority to make decisions promptly?

LMM’s project experience includes complex automotive installations requiring coordination among rigging, electrical, HVAC, civil, pipefitting, equipment vendors, and owner representatives. Our in-house project management teams develop installation schedules, coordinate qualified subcontractors, and self-perform critical portions of industrial work.

That combination can help an IPD team evaluate equipment movement, building access, lift plans, installation sequences, utility readiness, and startup requirements while changes are still manageable.

Frequently asked questions about IPD

Is IPD the same as design-build?

No. Design-build places design and construction under one primary contract, but it does not necessarily include shared financial risk and reward among the owner, designer, builder, and key trades, which a formal IPD agreement does.

Can a project use IPD principles without a multi-party contract?

Yes. A project can use early trade involvement, open-book estimating, shared planning, and collaborative meetings under another delivery method. Using a few collaborative practices, however, does not automatically create a formal IPD project.

Does IPD mean every participant votes on every decision?

No. Collaborative decision-making does not mean every participant votes on every issue. The agreement should define who has authority, how decisions are elevated, and what happens when the team cannot reach agreement.

Does IPD eliminate project risk?

No. Early input does not eliminate project risk. It gives the team more time to identify, assign, and reduce that risk before it reaches the field.

When is IPD not the right choice?

For straightforward work with a stable scope, design-bid-build may be appropriate. IPD requires transparency, early commitment, disciplined cost management, and participants who are willing to place project outcomes ahead of narrow scope interests.

Who signs the multi-party IPD agreement?

The principal participants sign it — typically the owner, the designer, the contractor, and the important trade partners. The agreement connects them through common project goals and defined decision-making procedures instead of separate contracts that isolate designers, contractors, and trades.

How does LMM participate as an IPD trade partner?

LMM participates in IPD teams as the single accountable partner for industrial heavy equipment moving solutions, coordinating rigging, machinery moving, crane service, millwright work, transportation, storage, electrical support, foundations, and commissioning preparation through one in-house project management team.

Because LMM self-performs critical portions of that work, lift, set, install, and commissioning preparation sit inside one accountable scope rather than across separate subcontracts. That lets LMM contribute equipment-movement, building-access, lift-plan, installation-sequence, utility-readiness, and startup information during design rather than after equipment reaches the site. You can review how that role is structured on our IPD trade partner for industrial equipment installation page.

If your team is evaluating integrated project delivery or asking what an IPD project would require for an upcoming industrial installation, contact LMM. We can contribute practical equipment-installation, rigging, logistics, electrical, and project-planning insight during the early stages of the work.