A boom truck is a hydraulic crane mounted on a commercial truck chassis. It is built for lighter picks and fast setup. An all terrain crane is a larger multi-axle crane that drives on the road under its own power and carries far more capacity and reach, but it needs more room to set up. For your plant move, the boom truck vs. all terrain crane choice depends on the site envelope and the heaviest pick at its working radius, not on the headline tonnage.
This guide compares capacity, radius, setup footprint and cost across the four machine classes that LMM (formerly Lee Machinery Movers) runs as part of its Michigan crane service: all terrain, rough terrain, carry deck and boom truck. It is written for the plant engineer or project manager who has to settle on a machine before the job is scoped.
How do boom truck, all terrain, rough terrain and carry-deck cranes compare?
Each class trades capacity and reach against footprint and access. Boom trucks set up fast for lighter picks, all terrain cranes reach farthest but need the most room, rough terrain cranes handle unpaved ground, and carry decks work inside the plant.
| Boom truck | All terrain crane | Rough terrain crane | Carry-deck crane | |
|---|---|---|---|---|
| Typical use | Lighter picks with fast setup; short-radius dock and building-edge picks | Picks that need more capacity and reach, including over a building, pipe rack or production line | Unpaved, uneven or muddy set-ups: substation pads, tank farms, gravel laydown areas | In-plant pick-and-carry: brings tools in, makes the lift, carries the old component out |
| Setup footprint | Smaller than an all terrain crane; can set close to the pick | Needs much more outrigger spread, counterweight tail swing and exclusion zone | Compact four-wheel machine | Designed for maneuverability in tight aisles and under overhead electric runs |
| Travel | Drives like a commercial truck; often keeps a flatbed to carry rigging or a small load | Travels on public roads under its own power; larger configurations can need extra trucks for counterweight | Does not drive on public roads; arrives on a trailer | Wheeled chassis with a flat deck that carries the load |
| Indoor suitability | Usually set up outside for dock or building-edge picks | Rarely; usually works outside, picking through a roof opening or at the dock | Built for outdoor yard and pad set-ups | Yes; dual-fuel propane options exist for enclosed spaces, and fuel and exhaust should be raised with your EHS lead |
What is the difference between a boom truck and an all terrain crane?
Choose a boom truck when the pick is light, the radius is short and setup time matters. Choose an all terrain crane when the pick needs more capacity or reach and the site has room for its outriggers and counterweight swing.
Both are mobile cranes, and both need a lift plan, a qualified operator and a ground check. The differences that matter show up in three places: how the machine reaches your plant, what it can lift at your radius, and how much ground it takes.
How does each crane get to your plant?
A boom truck drives like a commercial truck and often keeps a flatbed behind the cab, so it can carry rigging or a small load and lift on arrival. Most run a telescopic boom. Articulating, or knuckle, boom versions fold compactly and handle the load differently, so confirm which type you are being quoted.
An all terrain crane is a purpose-built multi-axle carrier. It travels on public roads under its own power and can steer in several modes, including crab steering, to work into a tight set-up position. Larger configurations can need extra trucks to bring counterweight to site, and that changes your mobilization plan.
Why is rated capacity different from capacity at your radius?
Capacity on a load chart drops as radius grows, so a crane rated well above the load’s weight can still be the wrong crane if it cannot set up close to the pick.
Every mobile crane’s headline rating applies at a short radius. As the boom extends and the load moves out, capacity drops. The number that matters is what the machine can pick at the distance from its centerline to the set point, at the height you need, with rigging weight included.
Compare load charts at your radius, not catalog maximums. A big number on the side of a crane tells you very little about the pick your site actually forces on it.
How much ground does each crane need to set up?
The area to clear is not the width of the truck. It is the full outrigger spread, plus the tail swing of the counterweight, plus the exclusion zone around the lift. An all terrain crane needs much more of all three. Next to a building wall or inside a congested yard, footprint is often what rules out the larger machine before capacity even comes up.
Why is a plant move a four-machine decision, not two?
LMM’s crane service runs from 15 to 500 tons and includes all terrain, rough terrain, carry deck and boom truck cranes, so the crane is chosen for the lift rather than the lift being fitted to the crane.
Inside a plant, the comparison usually widens. LMM’s crane service covers 15 to 500 tons across all terrain, rough terrain, carry deck and boom truck machines, so your choice is made among four classes rather than forced into two. On the right pick, either of the other two can beat both.
When should you use a rough terrain crane?
Choose a rough terrain crane when the set-up area is unpaved, uneven or muddy and the yard surface would stop a road crane.
A rough terrain crane is a compact four-wheel machine built for unpaved, uneven or muddy set-ups: an outdoor substation pad, a tank farm, a gravel laydown area. It does not drive on public roads. It arrives on a trailer, which has to be planned into mobilization and into the route from the gate to the set-up position. When your yard surface would stop a road crane, rough terrain is usually the first class to look at.
When should you use a carry-deck crane?
Choose a carry-deck crane when the pick is inside the plant, in tight aisles or under overhead electric runs, or when the load has to be lifted and carried across the floor.
A carry-deck crane puts a telescopic boom on a wheeled chassis with a flat deck that carries the load. Cranes Today reports that carry-deck cranes range from 2.5 to 25 US tons, with 9–15 US tons the most popular capacities. The same Cranes Today analysis notes that carry decks are designed for maneuverability in tight aisles and under overhead electric runs, and that dual-fuel propane options exist for enclosed spaces.
That makes the carry deck the machine that brings tools in, makes the lift and carries the old component out. Fuel and exhaust are an access constraint indoors, so raise them with your EHS lead before the machine class is locked.
When does a plant move need two machines?
Choose a two-machine plan when the pick crosses from yard to floor. An outdoor crane offloads at the dock, and a carry deck or rigging crew takes the machine inside.
A common plant pattern pairs an outdoor crane with in-plant equipment. A boom truck or all terrain crane offloads the machine at the dock. A carry deck or a rigging crew takes it inside to the foundation. Whenever your pick crosses from yard to floor, price this option alongside the single-machine plan.
How do you match the crane class to the pick?
Check the site envelope first, then capacity at radius, then the number of picks and days. Starting with tonnage is how a site ends up with a crane that can’t set up.
Run these four steps in order. The envelope comes first, then capacity at radius, then duration. Jumping straight to tonnage is how a site ends up with a crane that can’t set up.
Step 1: Is the pick inside the building, at the dock, or in the yard?
An in-building pick points to a carry deck or rigging methods such as skates and jack-and-slide. A dock or building-edge pick usually means a boom truck or all terrain crane set up outside. An unpaved yard points to rough terrain.
Step 2: What does the governing clearance and the surface allow?
Find the lowest door header or overhead run on the route, the slab or yard surface rating, and the space available for outriggers. Our crane lift site access walkthrough covers that check in full. On the ground itself, OSHA’s construction crane standard requires that equipment not be assembled or used unless ground conditions are firm, drained and graded sufficiently so that, with supporting materials if necessary, the manufacturer’s specifications for support and degree of level are met.
Step 3: What is the heaviest pick at its working radius?
Weigh the load including rigging, measure the radius from the set-up position to the set point, and check that against the chart. A small machine set close often outperforms a large machine pushed back by obstructions. That is the practical case for a boom truck on a short-radius dock pick. It is also the case for an all terrain crane when the pick has to reach over a building, a pipe rack or a production line.
Step 4: How many picks, over how many days?
One or two quick picks favor the machine with the fastest setup and teardown. A multi-day installation sequence can justify the larger machine’s setup time, because that time is spread across every pick that follows.
What drives the cost of a crane pick?
The most cost-effective machine is the smallest one that can safely handle your heaviest pick at its working radius inside the site envelope. Oversizing adds mobilization, setup time and footprint. Undersizing stalls the job or forces a second mobilization. Either way, the day rate is rarely the whole story.
What does mobilization add to the cost?
Getting the machine to your plant is a real line item. A rough terrain crane is trailered. Larger all terrain configurations can need support trucks for counterweight. Some travel routes need road-permit coordination. And the rigging crew has to be on site whichever machine shows up.
How do setup and teardown hours affect cost?
For a plant engineer, the clock that matters is the production window. Line-down hours lost to a slow setup can outweigh the difference between two machines’ day rates. Ask how long each option takes to set, rig and tear down, then hold that against the hours you actually have.
How do ground prep and the wrong machine affect total lift cost?
Mats, ground improvement and engineering for a soft surface all add cost, and a larger machine may need more of them. The most expensive outcome is the wrong machine: a crane that arrives and can’t set up, or can’t make the pick at the radius your site allows. Aim for the lowest total lift cost with the right-sized machine, not the lowest day rate.
Which crane fits common plant scenarios?
These are planning patterns, not project results. Every site still needs its own lift plan.
Which crane sets a rooftop HVAC unit or process skid from the yard?
Choose a boom truck when it can set close and the radius stays short. Choose an all terrain crane when the set point is deep across the roof or the crane has to stay back from the building line.
The governing constraint is how far the set point sits across the roof. More on cranes in industrial HVAC installation.
Which crane offloads a machine tool or press at the dock and takes it inside?
Choose an outdoor crane for the offload and a carry deck, rigging skates or jack-and-slide for the move to the foundation.
Here the constraint is the handoff. The handoff between lift and move is where days are lost. That is why it belongs in the same plan as your new equipment installation or industrial machinery relocation.
Which crane sets a transformer, tank or generator on an outdoor pad?
The ground decides this one. On gravel or uneven ground, the answer is usually a rough terrain crane, or an all terrain crane on prepared mats, depending on radius and access. Step 2 settles it.
Which crane suits a new-line installation with dozens of picks?
Repositioning drives the choice. Weigh setup time per relocation against capacity. A smaller machine that can move between set-ups quickly can beat a large crane that has to stay put and reach.
Who selects the crane and carries out the lift?
LMM is the single accountable partner for industrial heavy equipment moving solutions. The team that picks your machine class is the team that rigs, lifts and sets your equipment, so no selection decision gets handed between vendors.
Why should machine choice and rigging be in the same plan?
Machine selection, rigging design and the move to the foundation are one sequence. Split them across separate companies and every handoff becomes a place for the schedule to slip. Our crane service runs 15 to 500 tons across all terrain, rough terrain, carry deck and boom truck machines, backed by 500+ pieces of owned equipment. See the crane and rigging fleet for the current lineup. We thrive in technically demanding environments, delivering results under tight timelines, limited access, and challenging conditions.
Who operates LMM’s cranes?
Every machine is operated by LMM crews with NCCCO certified crane operators. Here is why NCCCO certification matters. We are signatory with the Operating Engineers, Millwrights and Laborers, founded in Pontiac, Michigan in 1997 and employee-owned since 2023. Once your machine class is chosen, the next decision is operated crane service vs. crane rental.
At LMM, safety isn’t just a priority — it’s a way of life. That shows up as training, clear communication and lift planning on every pick.
When you are ready to choose, send the pick details or call (248) 499-6086. Having these ready speeds up the answer:
- Load weight, with rigging
- Dimensions and center of gravity
- Pick and set locations
- Governing clearance on the route
- Slab or yard surface rating
- Your production window
Questions plant teams ask when choosing a boom truck or all terrain crane
Is a boom truck really a crane?
Yes. A boom truck is a hydraulic crane on a commercial truck chassis. Plan it like any crane: a lift plan, a qualified operator and a ground check before setup. The truck chassis changes how it travels, not how seriously the lift should be treated.
Can an all terrain crane work inside a plant?
Rarely. Its size, outrigger spread and counterweight swing usually keep it outside, picking through a roof opening or at the dock. In-building picks usually go to carry-deck cranes or rigging methods, which is the main reason a plant move ends up as a four-machine decision.
Is the bigger crane always the safer choice?
No. An oversized crane needs more footprint and setup time, and it can force a set-up position farther from the pick. That extra distance works against it at radius, so a larger machine pushed back can have less usable capacity than a smaller one set close.
Who should choose the machine class: the plant or the crane provider?
Both have a role. Your plant supplies the envelope data: clearances, surface ratings, access and production window. The crane team matches class and size against load charts in the lift plan. Our guide to building a critical lift plan walks through that process.
Who is responsible for ground conditions under the crane?
Responsibility for preparing the ground is typically set by site control and the contract, often resting with the controlling entity on the project, while the crane team confirms the ground meets the machine’s support needs before setup. Agree in writing who prepares, who verifies and who supplies mats before mobilization. This is general guidance; confirm the specifics for your project with your contract team.